Can Thai Binh 2 Thermal Power Plant generate electricity in 2020 if problems are not solved?

VCN- Thai Binh 2 Thermal Power Plant project has achieved some progress, but so far this project has not solved the "vital" problem financially, potentially affecting the progress of commercial electricity generation.
can thai binh 2 thermal power plant generate electricity in 2020 if problems are not solved Despite high prices, we need to take into account gas-fired power
can thai binh 2 thermal power plant generate electricity in 2020 if problems are not solved Single solar power price: Concerns about less competition, grid overload
can thai binh 2 thermal power plant generate electricity in 2020 if problems are not solved
The overall progress of the Thai Binh 2 Thermal Power Plant project is currently more than 84 percent. Photo: PVN

Overall progress of more than 84 percent

Thai Binh 2 Thermal Power Plant project has a total investment (2nd adjustment) of more than VND 41 trillion, so far the overall progress reaches more than 84 percent. In particular, most of the main construction items of the project have been basically completed and are in the stage of completion.

According to the Vietnam Oil and Gas Group (PVN), the specific progress of the project is as follows: Design reaches 99.6 percent; signing the contract of procurement reaching 99.71 percent; processing, manufacturing and transportation reached 93.89 percent; construction of 82.2 percent and test run 3.6 percent.

This is one of the typical slow progress projects of PVN. According to PVN, up to now, the project has recorded some achievements, including important milestones in construction work. Specifically, from September 23 to September 26, Thai Binh Thermal Power Plant Project 2 successfully energised the T3 transformer and conducted 72 hours of electrical immersion.

At 9 o'clock on October 29, the general contractor and the test experts successfully energised the 933A, B circuit breakers from 220kV grid. The national electricity system was supplied to the medium and low voltage for trial operation of the plant. This self-powered power source is used to test plant systems such as water treatment system, air-conditioning system, fire protection system, auxiliary boiler system, etc.

To achieve these milestones, related work items such as 220kV distribution yard, Central Control House, medium voltage, low voltage electrical system, etc. must all be completely installed beforehand to be ready for receiving reverse power.

“These are very important items that are considered the heart of the factory. Successful energising ensures a more stable and higher quality power source for commissioning,” PVN said.

Still cannot solve the "vital" problem

Although there have been some new developments, according to PVN, during implementation, the Thai Binh 2 Thermal Power Project has encountered difficulties in many aspects, especially issues such as: Slow cash flow, difficulties in arranging capital and shortage of human resources, especially highly qualified human resources.

In addition, the recommendations of PVN to the Government to remove the financial mechanism for the project, though agreed by the ministries and branches, have not been finalised by authorities in solving difficulties and problems of the project, especially recommendations on the use of equity in excess of the capital structure ratio of the project.

"This is a vital issue to bring the project into operation in 2020, ensuring the effectiveness of the project for the national electricity source, contributing to the overall economic development of the country," PVN stated.

At the end of July, the Steering Committee of the national key electricity projects, Minister of Industry and Trade Tran Tuan Anh and the State Capital Management Committee at the enterprise and Relevant agencies and agencies had a direct meeting at Thai Binh 2 Thermal Power Plant project.

Speaking at the meeting, Tran Sy Thanh, Chairman of PVN's Board of Directors, said: “Currently, finance is one of the four main issues at Thai Binh 2 Thermal Power Plant. Everything requires money. If there is no early decision, the project will close early.”

Also according to Thanh, the project has many difficulties and Vietnam Petroleum Construction Joint Stock Corporation (PVC) has made many violations. In addition, when the financial institutions cut credit, the project can no longer borrow. However, it is more dangerous to replace a general contractor for a project. Currently, PVN has directly taken part in, directed and operated all issues from people, capital, and planned to carry out when they have money.

In the coming time, PVN said that, besides the efforts of PVN, the Project Management Board, it is necessary to pay close attention, close decisions and timely resolution of authorities to achieve the goals of commercial generating of unit 1 in December 2020 and unit 2 in the first quarter of 2021 as requested by the Prime Minister stated in the resolution of the Government's regular meeting of August 2019.

By Thanh Nguyen/ Huu Tuc

Related News

Thai Binh seeks trade-investment partnership with Australian firms

Thai Binh seeks trade-investment partnership with Australian firms

The Vietnam-Australia trade and investment promotion forum and a conference promoting trade and investment in Vietnam's northern province of Thai Binh took place in Sydney on September 11, aiming to facilitate direct contact and exchange of cooperation, business, and investment opportunities between Vietnamese and Australian government agencies, organisations, and firms.
Ministry proposes new electricity tariffs

Ministry proposes new electricity tariffs

The Ministry of Industry and Trade (MoIT) has released a draft of the Prime Minister's decision on the structure of retail electricity tariffs for public feedback. The draft proposes a new pricing scheme based on a percentage of the average retail price of electricity for different groups of users.
Synchronous solutions in energy conversion

Synchronous solutions in energy conversion

VCN - According to Mr. Hoang Tien Dung, Director of the Department of Electricity and Renewable Energy (Ministry of Industry and Trade), Vietnam is taking the first steps in the transition from traditional energy to green and cleaner renewable energy. The energy transition process requires a comprehensive approach with the participation of all economic sectors in society with many synchronous solutions.
Bringing green energy from the Central Highlands

Bringing green energy from the Central Highlands

VCN - With a series of projects being implemented, the endless wind source of the Central Highlands is being turned into electricity for production activities. Customs units here have contributed significantly in supporting these projects to execute on schedule, bringing a huge source of budget revenue for localities, in the context that many other sources of revenue were sharply reduced due to the pandemic.

Latest News

Enterprises want clearer regulations on seafood production

Enterprises want clearer regulations on seafood production

There is a lack of consistency among existing legal documents on seafood production, making it difficult for enterprises to comply.
Vietnam ranks fifth among aquatic product suppliers for Singapore

Vietnam ranks fifth among aquatic product suppliers for Singapore

Vietnam jumped one place to become the fifth largest exporter of aquatic products to Singapore for the first time in the first quarter of this year, according to its Trade Office in the city state.
Forum seeks to increase PPP investment effectiveness

Forum seeks to increase PPP investment effectiveness

Investment cooperation in the public-private partnership (PPP) form is seen as a strategic option to mobilise private investment and improve public service delivery. However, the implementation of PPP projects in Vietnam still faces a lot of difficulties and obstacles, leading to a low number of successful projects and making the private economic sector cautious.
Linking businesses with cooperatives to increase the value chain

Linking businesses with cooperatives to increase the value chain

VCN - The issue of linking the value chain between domestic production units still has many "bottlenecks" that need to be resolved. In particular, solving the "problem" of linking businesses with cooperatives will help improve efficiency as well as meet the requirements of collective economic development.

More News

Vietnam has a trade deficit of over US$17 billion with China

Vietnam has a trade deficit of over US$17 billion with China

VCN – In the first quarter 2024, Vietnam-China trade reached US$43.6 billion. The country had a large trade deficit.
Tra fish export to UAE jumps 67% in Q1

Tra fish export to UAE jumps 67% in Q1

Vietnam’s tra fish export to the United Arab Emirates (UAE) reached more than 7 million USD in the first quarter of this year, a rise of 67% against the same period last year, statistics of the General Department of Customs showed.
Pepper prices continue increase trend

Pepper prices continue increase trend

Pepper prices are forecast to soon exceed 100,000 VND per kilo on the domestic market.
More efforts needed to maintain export growth to China: Insiders

More efforts needed to maintain export growth to China: Insiders

Exporters should further strengthen trade connections and improve the quality of their goods to sustain export growth to China as this is no longer a "lenient" market, said insiders.
It is expected that there are higher orders and revenue in the second quarter from European businesses

It is expected that there are higher orders and revenue in the second quarter from European businesses

VCN - The Business Confidence Index (BCI) according to a survey by the European Business Association in Vietnam (EuroCham) reached 52.8 in the first quarter of 2024 - the highest level since 2022, showing increasing confidence in Vietnam's European business community.
Vietnamese rice prices on the hike

Vietnamese rice prices on the hike

The prices of Vietnamese paddy and rice continued to increase last week, according to the the Vietnam Food Association (VFA).
FDI flow into garment and textile sector bounces back

FDI flow into garment and textile sector bounces back

The flow of foreign direct investment (FDI) into the Vietnamese garment and textile sector has rebounded thanks to the country’s sound investment climate and abundant workforce as well as its open economy, according to insiders.
Investors play a key role in developing the industrial park system

Investors play a key role in developing the industrial park system

VCN - Dr. Phan Huu Thang, Chairman of the Executive Committee of the Vietnam Industrial Park Finance Association, former Director of the Foreign Investment Department (Ministry of Planning and Investment), said that basically, developing an industrial park successfully or not mainly depends on businesses, entrepreneurs - industrial park investors.
Find ways to a corporation for businesses in industrial parks

Find ways to a corporation for businesses in industrial parks

VCN - The country has nearly 300 industrial parks in operation, but with the requirement to join the global value chain, the issue of linkage and connection between businesses in industrial parks and industrial clusters needs to be concentrated on more.
Read More

Your care

Latest Most read
Enterprises want clearer regulations on seafood production

Enterprises want clearer regulations on seafood production

There is a lack of consistency among existing legal documents on seafood production, making it difficult for enterprises to comply.
Vietnam ranks fifth among aquatic product suppliers for Singapore

Vietnam ranks fifth among aquatic product suppliers for Singapore

Vietnam jumped one place to become the fifth largest exporter of aquatic products to Singapore for the first time in the first quarter of this year, according to its Trade Office in the city state.
Forum seeks to increase PPP investment effectiveness

Forum seeks to increase PPP investment effectiveness

Investment cooperation in the public-private partnership (PPP) form is seen as a strategic option to mobilise private investment and improve public service delivery. However, the implementation of PPP projects in Vietnam still faces a lot of difficulties and obstacles, leading to a low number of successful projects and making the private economic sector cautious.
Linking businesses with cooperatives to increase the value chain

Linking businesses with cooperatives to increase the value chain

VCN - According to experts, in value chain links, agricultural cooperatives both play a role in promoting links between farmer households through collective economic activities to organize production and promote vertical linkages with businesses along the
Vietnam has a trade deficit of over US$17 billion with China

Vietnam has a trade deficit of over US$17 billion with China

VCN - According to the latest statistics of the General Department of Customs, the import-export turnover between Vietnam and China in March reached US$ 16.32 billion, including Vietnam's exports achieved US$5.15 billion, imports reached US$11.17 billion.
Mobile Version