Series of projects behind schedule, leading to serious shortage of electricity in the South

VCN - As many big projects are behind schedule a serious shortage of electricity in the near future is inevitable. Notably, the threat of electricity shortages in the Southern region is serious.
series of projects behind schedule leading to serious shortage of electricity in the south 11011 Part 3: Is electricity saving a “cure”?
series of projects behind schedule leading to serious shortage of electricity in the south 11011 In the "thirst" of electricity – Part 1: Lack of electricity is no longer a risk
series of projects behind schedule leading to serious shortage of electricity in the south 11011 It's necessary to make electricity retail price transparent
series of projects behind schedule leading to serious shortage of electricity in the south 11011 Electricity, aviation companies forecast for a great 2019
series of projects behind schedule leading to serious shortage of electricity in the south 11011
The electricity industry is facing many difficulties to ensure sufficient electricity supply. Photo: Nguyen Thanh

47 large projects behind schedule

According to the Adjusted Power Planning VII, the total capacity of power sources expected to be put into operation for 2016-2020 on the whole system is 21,650 MW.

Currently, power projects implemented in three forms of investment are: projects invested by state-owned corporations including Vietnam Electricity (EVN), Vietnam Oil and Gas Group (PVN), and Vietnam National Coal and Mineral Industries Holding Corporation Limited (TKV); projects invested in the form of Build-Operate-Transfer (BOT); and projects invested in the form of Independent Power Projects (IPP).

The latest report by the Ministry of Industry and Trade on the implementation of electricity projects in the Adjusted Power Planning VII showed that of the 62 projects with a large capacity of over 200 MW, 15 projects were on schedule, while the remaining 47 projects were behind schedule or have not determined the progress compared to the schedule stated in the Adjusted Power Planning VII.

Specifically, in the total capacity for 2016-2020 (21,651 MW), EVN invested 7,185 MW (accounting for 33.2%) with 23 projects of all kinds; non-EVN power sources were 14,465 MW (accounting for 66.8%). Of the 23 projects invested by EVN, 10 projects were on schedule, and 13 projects were behind schedule or delayed. So far, 8 projects by EVN have completed construction and been put into operation, 4 projects are under construction, and 11 projects are carrying out procedures.

According to the Plan, PVN was assigned to be the investor of 8 source projects with a total capacity of 11,400 MW. There are 3 projects for 2016-2020 and 5 projects for 2021-2025. Up to now, all 8 projects have faced difficulties and obstacles and it is difficult to complete them on schedule. Currently, PVN is building 3 projects, but all are 2-3 years behind schedule; PVN is implementing investment procedures for 4 projects but they are expected to be behind schedule from 2.5-3.5 years compared to the Adjusted Power Planning VII; and 1 project of PVN has been offered to other investors.

For TKV, the number of projects implemented is four with a total capacity of 2,950 MW. Of which 2 projects are in the 2016-2020 period, and 2 projects are in the 2021-2030 period. Currently, all 4 projects are behind schedule for 2 years or more.

There are 15 BOT projects, of which one is for 2016-2020, and the rest will be implemented for 2021-2030. According to the evaluation, only 3 projects are able to be on schedule, and 12 projects are behind schedule or unable to determine the progress because of problems in negotiations.

IPP projects are also not very positive because of the 8 projects with a set capacity of 7,390 MW, only 1 project is on schedule and 2 projects are likely to be on schedule. The remaining projects have not determined the completion time.

In the plan, 5 power source projects (of which 1 project was out of planning) are for the 2021-2030 period without investors.

Regarding renewable energy projects, the Ministry of Industry and Trade stated up to now, the Government and the Ministry of Industry and Trade have approved 130 solar power projects with a capacity of about 8,500 MW and wind power projects with a capacity of about 2,000 MW. However, the renewable energy projects are concentrated in low load areas – the 110-500kV power grid infrastructure in these areas has not met the transmission requirements.

Severe power shortage in the South

According to the Adjusted Power Planning VII, to meet the needs of economic growth, by 2020, the total capacity of power plants will be about 60,000 MW; this number will be 96,500 MW by 2025 and it will reach 129,500 MW by 2030.

A total of 21,651 MW will be put into operation for 2016-2020; 38,010 MW will be put into operation for 2021-2025; and a total of 36,192 MW will be put into operation for 2026 -2030.

In fact, the total capacity of power sources that can be put into operation in the period of 2016-2030 is expected to be about 80,500 MW, lower than the Adjusted Power Planning VII by more than 15,200 MW, of which the years from 2018-2022 will be the main period for shortages. Many projects in this period are delayed for the period of 2026-2030 and most of them are thermal power projects in the South.

According to calculations, for power source projects put into operation in 2019-2020, the electricity system can meet the national electricity demand. However, it is necessary to mobilize more oil-fired thermal power with a corresponding output of 1.7 billion KWh in 2019 and 5.2 billion kWh in 2020. In the case that generating sets do not meet the operational reliability requirements, or do not have enough fuel (coal, gas) for electricity generation, Vietnam may face the risk of electricity shortages by 2020.

In the years from 2021-2025, although the maximum power source will be mobilized, the electricity system will likely fail to meet the demand for additional charge and there will be a shortage of electricity in the South, with a shortfall increasing from 3.7 billion kWh (in 2021) to nearly 10 billion kWh (in 2022). The highest shortage will be about 12 billion kWh in 2023, and then will gradually decrease to 7 billion in 2024 and 3.5 billion kWh in 2025.

According to the Ministry of Industry and Trade, the main reason for the lack of electricity in the South being higher than previous calculations is because the progress of Block B, Blue Whale gas projects was 9 months to 1 year behind schedule compared to the plan; Kien Giang 1&2 Power Plants did not meet the completion schedule in the 2021-2025 period, even delayed until after 2030; and the O Mon III project was delayed to 2025. If the Long Phu 1 power project does not meet the completion schedule in 2023, the power shortage in the South in the years 2024-2025 will be more serious.

series of projects behind schedule leading to serious shortage of electricity in the south 11011 It is too far away to ensure electricity security in Vietnam

VCN- According to Mr. Le Van Luc, Deputy Director of the Department of Electricity and Renewable Energy ...

Currently, the Ministry of Industry and Trade has actively promoted solutions to ensure power supply for the upcoming period; and simultaneously coordinated with relevant ministries and agencies to remove difficulties in mechanisms and policies in order to promote construction investment projects, meeting electricity requirements for socio-economic development.

By Thanh Nguyen/ Ha Thanh

Related News

Vietnam

Vietnam's stock market to develop strongly and sustainably

VCN - This was emphasized by Minister of Finance Nguyen Van Thang at the Conference to review the work of 2024 and deploy the work of 2025 of the State Securities Commission (SSC) held on the afternoon of December 18.
Challenges in reviving stalled projects

Challenges in reviving stalled projects

VCN - Recently, some "frozen" real estate projects have shown signs of restarting. However, successfully reviving these projects is no simple task for businesses (DN) due to the numerous difficulties and challenges they face.
Customs control and prevent many drug trafficking cases in the South

Customs control and prevent many drug trafficking cases in the South

VCN - Proactively grasping the situation and controlling the assigned areas, recently, the Southern Anti-Drug Smuggling Control Team (Team 6) under the Anti-Smuggling and Investigation Department, General Department of Customs, has coordinated to detect and prevent many drug smuggling cases through the Southern region.
Accelerate implementation of solutions to disburse public investment capital

Accelerate implementation of solutions to disburse public investment capital

VCN - Facing the impact of storm No. 3 on economic growth, many experts continue to believe that public investment will play a key role in economic recovery and growth for the entire year of 2024. However, there is only one quarter left until the end of 2024. The target of disbursing at least 95% of investment capital is facing many difficulties.

Latest News

Seafood exports expected to exceed $10 billion in 2025: expert

Seafood exports expected to exceed $10 billion in 2025: expert

The achievement of the $10 billion export milestone in 2024 is attributed in part to efforts to open and strengthen connections with key markets such as the US and the EU.
Top 10 Reputable Animal Feed Companies in 2024: Efforts to survive the challenges of nature

Top 10 Reputable Animal Feed Companies in 2024: Efforts to survive the challenges of nature

VCN - In the Report announcing the Ranking of Top 10 Reputable Animal Feed Companies in 2024 on December 12, 2024, Vietnam Report Joint Stock Company said that Vietnam's animal feed industry has faced many challenges from natural disasters and epidemics. But overcoming all, the industry continues to survive and has confidence in the future.
Vietnam's import-export surges 15.3%

Vietnam's import-export surges 15.3%

Vietnam's total import-export turnover reached 745 billion USD as of December 14, marking a robust 15.3% growth compared to the same period in 2023, according to the General Department of Vietnam Customs.
More Vietnamese firms interested in Saudi Arabia: Ambassador

More Vietnamese firms interested in Saudi Arabia: Ambassador

An increasing number of Vietnamese enterprises are showing interest in Saudi Arabia, particularly in the sectors of Vietnam's advantages and the Middle East country's needs, a diplomat has said.

More News

“Give and Take” in the Value Chain of the CPTPP Market

“Give and Take” in the Value Chain of the CPTPP Market

VCN - Vietnamese businesses have many opportunities and advantages if they take advantage of resources from imports and technology transfers when joining the supply chains of FDI companies within the CPTPP.
Binh Dinh province works to attract investment from Japan

Binh Dinh province works to attract investment from Japan

The People’s Committee of Binh Dinh province on December 18 inked a cooperation deal with the Japan - Vietnam Friendship Association of Sakai city as part of the south-central province’s efforts to attract more investment and development resources from the Northeast Asian country.
Agricultural, forestry and fishery exports “reach the target” early

Agricultural, forestry and fishery exports “reach the target” early

VCN - According to a report from the Ministry of Agriculture and Rural Development, the export turnover of agricultural, forestry and fishery products in November 2024 is estimated at US $5.3 billion, up 13.9% compared to November 2023. It is notable that it not only “reaching the finish line” early, the agricultural sector also exceeded the annual plan by over US $ one billion.
Thailand remains Vietnam’s biggest trading partner in ASEAN

Thailand remains Vietnam’s biggest trading partner in ASEAN

The activities conducted by the Vietnam Trade Office in Thailand in 2024 have enriched the trade and investment relations between the two countries, contributing to helping Thailand maintain its position as Vietnam's largest trading partner in the Association of Southeast Asian Nations (ASEAN), according to Le Huu Phuc, Vietnam's Trade Counsellor in Thailand.
Rubber value soars in 2024: VRA

Rubber value soars in 2024: VRA

All Vietnam's rubber’s top 15 export markets saw growth in export values in 2024, with Malaysia recording the highest increase, expanding fivefold, followed by Sri Lanka at 3.7 times, according to the Vietnam Rubber Association (VRA).
Vietnamese businesses struggle to access green finance

Vietnamese businesses struggle to access green finance

VCN - Green finance is gradually becoming an indispensable tool in Vietnam to support businesses, promote sustainable development, and move towards the goal of Net Zero. However, the path to accessing green capital is full of barriers, especially for small and medium enterprises.
E-commerce: a gateway to boost Vietnamese commodities in the UK market

E-commerce: a gateway to boost Vietnamese commodities in the UK market

E-commerce stands out as a promising channel to further enhance Việt Nam’s trade presence in this dynamic market.
Agro-forestry-fisheries exports top 62 billion USD in 2024

Agro-forestry-fisheries exports top 62 billion USD in 2024

Vietnam’s agro-forestry-fisheries exports are projected to reach over 62 billion USD in 2024, and continue to grow next year, heard at a conference in Ho Chi Minh City on December 16.
Removing “bottlenecks” for digital transformation in industrial production

Removing “bottlenecks” for digital transformation in industrial production

VCN - Although implementing digital transformation towards smart production creates many opportunities, it also poses significant challenges for businesses, especially in terms of investment costs and human resources.
Read More

Your care

Latest Most read
Seafood exports expected to exceed $10 billion in 2025: expert

Seafood exports expected to exceed $10 billion in 2025: expert

The achievement of the $10 billion export milestone in 2024 is attributed in part to efforts to open and strengthen connections with key markets such as the US and the EU.
Top 10 Reputable Animal Feed Companies in 2024: Efforts to survive the challenges of nature

Top 10 Reputable Animal Feed Companies in 2024: Efforts to survive the challenges of nature

VCN - In the Report announcing the Ranking of Top 10 Reputable Animal Feed Companies in 2024 on December 12, 2024, Vietnam Report Joint Stock Company said that Vietnam's animal feed industry has faced many challenges from natural disasters and epidemics.
Vietnam's import-export surges 15.3%

Vietnam's import-export surges 15.3%

Vietnam's total import-export turnover reached 745 billion USD as of December 14, marking a robust 15.3% growth compared to the same period in 2023, according to the General Department of Vietnam Customs.
More Vietnamese firms interested in Saudi Arabia: Ambassador

More Vietnamese firms interested in Saudi Arabia: Ambassador

An increasing number of Vietnamese enterprises are showing interest in Saudi Arabia, particularly in the sectors of Vietnam's advantages and the Middle East country's needs, a diplomat has said.
“Give and Take” in the Value Chain of the CPTPP Market

“Give and Take” in the Value Chain of the CPTPP Market

Vietnamese businesses have many opportunities and advantages if they take advantage of resources from imports and technology transfers when joining the supply chains of FDI companies within the CPTPP.
Mobile Version