Ministry of Construction gives "ultimatum" on disbursement of public investment

VCN - The Ministry of Construction recently issued a directive on speeding up the implementation and disbursement of the 2021 public investment capital plan, requiring 100% completion of the capital plan assigned by the end of December 31, 2021.
The Ministry of Construction requested to soon complete the final settlement documents of completed bidding packages of the National Assembly Building project. Source: Internet.
The Ministry of Construction requested to soon complete the final settlement documents of completed bidding packages of the National Assembly Building project. Source: Internet.

Disbursement reached 22.2% of the allocated plan

According to the Ministry of Construction, units have made great efforts to accelerate the implementation and disbursement of public investment capital in 2021.

However, implementation is still limited, is not effective, not drastic in some units, the leaders of some units are not thorough, lack urging, inspection and responsibility in the implementation of the project, coordination in handling work and organisation of implementation is still not tight, there is still the situation of passing and avoiding responsibility.

Discipline in public investment is not strict, so some projects are implemented slowly and implementation is not on time; a number of projects have completed volume, but the procedures for acceptance, payment and finalisation are slow, leading to a low disbursement value of the public investment capital plan in 2021, affecting plan implementation from the Ministry of Construction.

Regarding investment projects using public investment capital, the Ministry of Construction said at the beginning of the year, the ministry assigned details of the 2021 State budget capital investment plan (phase 1) for investment projects meeting the conditions with capital of 322.52 billion VND.

The remaining capital (VND 353,719 billion) would be delivered immediately after the National Assembly approves the medium-term public investment plan for 2021-2025. In the first six months of the year, disbursed public investment capital was 70.54 billion dong, reaching 22.2% of the plan.

Implementing the medium-term public investment plan for 2021-2025, the Ministry of Construction has completed a detailed capital allocation plan, finished the appraisal and approved investment policies for projects in the medium-term investment portfolio in 2021-2025 with a total expected capital of VND 3,006.9 billion, which has been submitted to the Ministry of Planning and Investment for appraisal.

For projects using economic public service funds, in 2021, the Ministry of Construction will manage 64 tasks and programmes (including 46 newly opened tasks) with a total budget of 28.83 billion dong.

Regarding ODA projects, in 2021 the Ministry of Construction is directly managing, implementing and coordinating 10 ODA programmes and projects with a total budget of VND 59.93 billion (of which, the counterpart is VND 17.26 billion and foreign capital is VND 42.67 billion).

100% of the 2021 capital plan must be completed by December 31, 2021

To ensure completion of the public investment capital plan assigned in 2021, the Minister of Construction requested heads of the affiliated units to urgently direct the synchronous, drastic and effective implementation of tasks, and solution.

Accordingly, speeding up the preparation of the project, the selection of contractors is in accordance with the law, and early starting the work, as well as conducting online bidding, ensuring publicity and transparency, and selection of qualified contractors.

Remove difficulties and obstacles, ensuring progress of works; expeditiously check and accept, make payment documents as soon as the volume is available, carry out the payment procedures of investment capital for the project within four days from is checked and accepted as prescribed, not to accumulate payments at the end of the year, not to cause outstanding debt for capital construction.

For example, for the construction investment project of the National Assembly House, the Ministry of Construction requested urging contractors and related units to speed up the completion of finalisation documents of completed bidding packages to timely disburse public investment capital in 2021.

Maximise human resources to complete the checking and payment procedures for contractors; complete final settlement documents for bidding packages audited by the State Audit, and submit them to the Ministry of Construction for verification and approval in accordance with regulations; handle problems or promptly report problems beyond their competence to the Ministry of Construction.

The Ministry of Construction also requires 100% of the capital plan assigned 2021 must be completed by the end of December 31, 2021. Investors must commit to the implementation schedule and disbursement of public investment capital in 2021 with the Ministry of Construction on a monthly basis.

By September 30, projects with a disbursement rate of less than 60% of the public investment capital plan assigned in 2021 (except for new construction projects in 2021 awaiting capital allocation after by the Prime Minister approved a medium-term public investment plan for the period of 2021-2025) will have their capital transferred to projects with good disbursement progress and lacking capital. The Ministry of Construction will review responsibility and take disciplinary measures against the head of the investors for the delay in implementation and disbursement.

The ministry also requested investors to focus on directing, inspecting, urging and promptly handling difficulties and problems in the disbursement of public investment capital, especially problems with investment procedures and procedures for checking, payment and the settlement of investment capital; attaching implementation and disbursement progress and project efficiency to the individual responsibility of the head and the person assigned to perform the task, considering them a criterion for assessing the level of work completion in 2021.

Resolutely and promptly handle organisations and individuals that violate and intentionally obstruct, causing difficulties, slow the implementation and disbursement progress of the 2021 public investment capital plan and promptly replace civil servants, public employees and employees being weak or having negative interferences on the performance of investment capital management tasks and in bidding.

For investors who do not meet their committed progress, are late in submitting the settlement report of completed projects, or do not reach 100% of the disbursement plan for public investment capital in 2021, the Ministry of Construction will handle the responsibility of the head of the investor, at the same time consider the transfer of the project investor, resolutely not allocate capital to start new projects, do not allow them to be the investor of other projects. The head of the unit must be subject to a specific disciplinary action and take responsibility fully before the Minister of Construction.

By Hoai Anh/ Binh Minh

Related News

Striving for revenue to rise by over 15% compared to assigned estimate

Striving for revenue to rise by over 15% compared to assigned estimate

VCN – At meeting on summarizing in financial budget October and deploying work program in November held by the Ministry of Finance on November 11, Deputy Minister of Finance Cao Anh Tuan requested to speed ​​up review budget work and quickly remove financial institutional bottlenecks.
Public investment spending up 1.8% in first 10 months of 2024

Public investment spending up 1.8% in first 10 months of 2024

VCN - Public investment from Vietnam’s state budget saw steady growth in the first ten months of 2024, reaching 64.3% of the annual target—an increase of 1.8% compared to the same period last year.
Removing many bottlenecks in regular spending to purchase assets and equipment

Removing many bottlenecks in regular spending to purchase assets and equipment

VCN - Decree No. 138/2024/ND-CP, which has just been issued, is expected to contribute to resolving bottlenecks in allocating funds for purchasing assets and equipment; renovating, upgrading, expanding, and constructing new construction items in projects that have been invested in and constructed in the past.
Removing legal hurdles in regular spending for capital assets

Removing legal hurdles in regular spending for capital assets

VCN - Mr. Bui Anh Binh, Deputy Director of the Department of Public Administration (Ministry of Finance) emphasized that the issuance of Decree No. 138/2024/ND-CP has created an important legal corridor, promptly removed obstacles, and created conditions for ministries, branches, and localities to proactively use regular expenditures to carry out tasks and projects outside the approved medium-term public investment plan, and to be proactive in performing assigned tasks.

Latest News

Monetary policy forecast unlikely to loosen further

Monetary policy forecast unlikely to loosen further

It will be difficult for the State Bank of Vietnam (SBV) to further loosen monetary policy due to a rising USD/VNĐ exchange rate pressure, experts said.
World Bank outlines path for Vietnam to reach high income status

World Bank outlines path for Vietnam to reach high income status

The World Bank (WB) has released a report which explores how Vietnam can upgrade its participation in global value chains to become a high-income country by 2045.
Strictly control public debt and ensure national financial security  2025

Strictly control public debt and ensure national financial security 2025

VCN – In order to achieve goal of strictly managing public debt and maintaining security and safety of the national financial system in 2025, it is necessary to ensure the borrowings and repayments of public debts is within the approved estimate; closely monitor public debt indicators to ensure that they are within the ceiling and warning thresholds approved by the National Assembly.
Revising the title of a draft of 1 Law amending seven finance-related laws

Revising the title of a draft of 1 Law amending seven finance-related laws

VCN - On November 19, 2024, the Standing Committee of the National Assembly (SCNA) discussed amendments and refinements to the draft of a law revising seven existing finance-related laws. Concluding the session, Vice Chairman of the National Assembly Nguyen Duc Hai emphasized the need for the Government to direct the drafting body and relevant agencies to collaborate closely to finalize a persuasive and widely supported report, ensuring the quality of the draft law for the National Assembly's consideration and decision.

More News

Transparency evates the standing of listed companies

Transparency evates the standing of listed companies

VCN - According to the Hanoi Stock Exchange (HNX), the number of companies placed under warning, control, or restricted trading on the listed and registered markets has increased over the past two years compared to 2022.
State-owned securities company trails competitors

State-owned securities company trails competitors

Contrary to the outstanding performances in the banking sector, the securities subsidiaries of major banks have yet to fully leverage their potential, despite numerous inherent advantages.
Strengthening the financial “health” of state-owned enterprises

Strengthening the financial “health” of state-owned enterprises

VCN - The state economy plays a key role in the socio-economic development process, but it is necessary to strengthen the financial health and competitiveness of state-owned enterprises (SOEs).
U.S. Treasury continues to affirm Vietnam does not manipulate currency

U.S. Treasury continues to affirm Vietnam does not manipulate currency

VCN - In its latest report, the U.S. Department of the Treasury has positively assessed Vietnam's monetary policy, reaffirming that Vietnam does not engage in currency manipulation.
Exchange rate fluctuations bring huge profits to many banks

Exchange rate fluctuations bring huge profits to many banks

Net profits from the foreign exchange trading segment of many banks have gained positive results thanks to a strong USD/VNĐ exchange rate fluctuations this year.
A “picture” of bank profits in the first nine months of 2024

A “picture” of bank profits in the first nine months of 2024

VCN - Pre-tax profits for banks during the first nine months of 2024 remained positive, exceeding 200 trillion VND, solidifying the sector's position as a market leader.
Many challenges in restructuring public finance

Many challenges in restructuring public finance

VCN - Restructuring public finance is an important step to improve state financial management, ensure resources are allocated reasonably and effectively, contributing to the country's sustainable development. In addition to the achieved results, the process of accelerating public finance restructuring also faces many pressures.
Tax declaration and payment by e-commerce platforms reduces declaration points and compliance costs

Tax declaration and payment by e-commerce platforms reduces declaration points and compliance costs

VCN - E-commerce platforms that declare and pay taxes on behalf of traders not only help to reduce the number of tax declaration points but also reduce the cost of compliance with administrative procedures for the whole society because only one point as the e-commerce trading platform implements tax deduction, payment and declaration on behalf of tens, hundreds of thousands of individuals and business households on the platform.
Disbursement of public investment must be accelerated: Deputy PM

Disbursement of public investment must be accelerated: Deputy PM

Deputy Prime Minister Ho Duc Phoc has called on ministries, agencies, and localities to accelerate the disbursement of public investment from now until the year-end and further tighten investment management.
Read More

Your care

Latest Most read
Monetary policy forecast unlikely to loosen further

Monetary policy forecast unlikely to loosen further

It will be difficult for the State Bank of Vietnam (SBV) to further loosen monetary policy due to a rising USD/VNĐ exchange rate pressure, experts said.
World Bank outlines path for Vietnam to reach high income status

World Bank outlines path for Vietnam to reach high income status

The World Bank (WB) has released a report which explores how Vietnam can upgrade its participation in global value chains to become a high-income country by 2045.
Strictly control public debt and ensure national financial security  2025

Strictly control public debt and ensure national financial security 2025

VCN - According to the plan for borrowing and repaying public debt and foreign debt of the country in 2025, the total borrowing demand of the Government in the year is expected to be at VND 815,238 billion, an increase of 20.6% compared to the Government'
Revising the title of a draft of 1 Law amending seven finance-related laws

Revising the title of a draft of 1 Law amending seven finance-related laws

On November 19, 2024, the Standing Committee of the National Assembly (SCNA) discussed amendments and refinements to the draft of a law revising seven existing finance-related laws.
Transparency evates the standing of listed companies

Transparency evates the standing of listed companies

According to the Hanoi Stock Exchange (HNX), the number of companies placed under warning, control, or restricted trading on the listed and registered markets has increased over the past two years compared to 2022.
Mobile Version