Disbursement on capital borrowed from aboard: How to solve difficulties?

VCN – Over the past eleven months, the disbursement of public investment capital borrowed from abroad by ministries and sectors reached just 34.65% of the plan assigned at the beginning of the year and 45.51% if calculated on the number of the plan in 2020 adjusted after cutting VND4,346 billion.
3118-1335-11-4221-xay-lap
Many projects have been allocated capital plans but are having to carry out project adjustment procedures. Source: Internet

No volume for disbursement

According to the Ministry of Finance, the biggest problem that caused the disbursement rate of ODA loans and concessional loans to be low is that there is no volume of completed construction, so there is no payment record leading to impossible disbursement.

The reasons include the impact of the Covid-19 pandemic, natural disasters and floods. Even in areas less affected by floods, the Ministry of Finance found that progress in implementing and submitting applications of capital withdrawal is still slow. This needs to be further clarified and more specific about the responsibilities of each stage. Additionally, there are many projects that have been allocated capital plans but have to implement project adjustment procedures (such as extending project implementation time, extending disbursement time, adjusting allocation of projects item using capital), adjusting loan agreements, so those projects do not have enough basis for disbursement.

Some projects have faced problems with the mechanism, so the allocation/re-lending to allocate capital for implementation in 2020 (for example: projects of the Vietnam Expressway Development Corporation (VEC) which borrowed from the Japan International Cooperation Agency (JICA) has not been approved by the competent authority to switch from re-lending to allocation).

Another problem is that, according to the special account disbursement method of some donors such as the World Bank (WB), Asian Development Bank (ADB) and JICA, many project owners have delayed implementation of returning documents for withdrawing from special accounts, sponsors approve dossiers of withdrawing supplementary funds in special accounts for small expenditures. Besides that, the preparation of capital withdrawal documents of project owners is not thorough, including incomplete, inaccurate, and inappropriate expenditure plans.

December is the peak month for concentrating to complete payment procedures. In particular, documents and evaluation sheets are made to determine the completed basic volume, and documents sent to the State Treasury to control expenditure, make payment notes, disbursement of capital withdrawal and closing the state budget settlement book.

Currently, the Ministry of Finance is working with the Ministry of Justice and relevant authorities, as well as the Office of the Government, to complete the draft Decree amending Decree No. 97/2018/ND-CP dated June 30, 2018 about on-lending ODA and foreign preferential loans of the Government, ensuring that the Decree after being revised, will simplify the process and procedures for appraisal and signing of on-lending contracts.

The ministries and sectors need to immediately report in a timely manner, if the capital plan must be adjusted within the units or if the total investment is increased, then report it to the Prime Minister. If the project ends in 2020, it needs to implement project adjustment and capital withdrawal procedures, it is necessary to promptly report to the competent authority to ensure the appropriate time for withdrawal. Ministries and sectors need to direct project management boards that have completed workloads early to the State Treasury to control expenditure, and send to the Department of Debt Management and External Finance, and donors for implementing disbursement procedures, ensuring recording of revenues and expenditures as well as disbursement procedures.

Timely reporting

To promote the disbursement of this special capital, as 2020 is coming to an end and will be a premise for 2021, the Ministry of Finance has proposed to the Government a number of solutions such as: proposing ministries and sectors, project owners to be responsible for urgently completing the procedures for investment, construction, migration and resettlement, and site clearance to implement the project; to completely handle the shortcomings and problems of large investment projects, focus on accelerating the disbursement of investment projects which have disbursement potential, projects that have completed investment procedures, and bidding, immediately implementing the signing of bidding packages with a "no objection" opinion of the sponsor.

Additionally, to strengthen the capacity of implementation of ODA projects at the governing body, investor and project management board levels, to ensure that the project management staff are capable and qualified. The ministries and sectors are also responsible for allocating enough reciprocal capital to pay in accordance with the assigned estimates; coordinate with the Ministry of Planning and Investment and the Ministry of Finance to solve problems.

The Ministry of Finance also requested donors to review and reduce unnecessary procedures, and speed up the approval time for issues that require no objection. For projects in the recruitment stage of consultants to set up total investment, it should have solutions to supervise the quality and progress of consultants, avoiding problems and delays that affect project implementation.

For proposals on cutting capital plans, ministries and sectors must determine which projects should be cut. Also, it is necessary to clarify which projects are completely disbursed in 2020, which projects can only partially disburse, coordinate with the Ministry of Planning and Investment to determine the amount of capital that has been allocated in the 2016-2020 period and the actual disbursed capital. If there was a shortage of capital and it is still available for disbursement in the following years, it must be proposed to include in the medium-term plan for the 2021-2025 period and the investment capital plan of 2021.

Regarding matters around adjusting investment policies and loan agreements, for programs and projects requiring adjustment of investment policies, the Ministry of Finance requests ministries and sectors to report to the Ministry of Planning and Investment to submit to the Prime Minister for approval of the investment adjustment policy. On the basis of the Prime Minister's decision on the investment adjustment policy, the Ministry of Finance will coordinate with the ministries and sectors in reporting to the Prime Minister on the adjustment of the time limit for disbursement and capital allocation under the loan agreements already signed and other adjustments to the loan agreement (if any) in accordance with the regulations, complying with the Law on State Budget and the Law on Public Debt Management.

By Hồng Vân/Thanh Thuy

Related News

Continue to publicly disburse public investment capital, many key projects have low rates

Continue to publicly disburse public investment capital, many key projects have low rates

VCN - The Ministry of Finance continues to publicize the disbursement rate of public investment capital plans of many key projects, notably that many projects and component projects have very low disbursement rates.
Public investment disbursement rate in 8 months reaches about 40.5% of the plan

Public investment disbursement rate in 8 months reaches about 40.5% of the plan

VCN - The low disbursement rates of some localities that have large disbursement plans, have greatly affected the overall disbursement rate of the whole country, the Ministry of Finance released.
Slow disbursement of public investment capital due to obstacles from policies

Slow disbursement of public investment capital due to obstacles from policies

VCN - Disbursement of public investment capital still has faced many obstacles, mainly focusing on mechanisms and policies related to specialized ministries.
Removing public investment bottlenecks

Removing public investment bottlenecks

VCN - Public investment is one of the three pillars promoting economic growth, along with consumption and export. However, the disbursement of public investment in many localities across the country is still slow due to problems in compensation, project site clearance, difficult and complicated land acquisition, land procedures, environmental impact assessment, project investment procedures, etc.

Latest News

State revenue in 8 months increased by about 18%

State revenue in 8 months increased by about 18%

VCN – In the first eight months of the year, the accumulated state revenue is estimated to increase by 17.8% year-on-year to VND1,335.6 trillion, meeting 78.5% of the estimate.
Challenges of collecting e-commerce tax losses

Challenges of collecting e-commerce tax losses

Digital transformation is an inevitable trend that changes the way goods and services are consumed and supplied, especially activities on digital platforms, making tax management more complicated.
Green finance brings both new opportunities, challenges to Vietnam: Experts

Green finance brings both new opportunities, challenges to Vietnam: Experts

The promotion of green and sustainable financial development has created both new opportunities and challenges for the financial system in Vietnam, according to experts.
Vietnam has 4 enterprises providing credit rating services

Vietnam has 4 enterprises providing credit rating services

VCN - The Ministry of Finance said that, according to the provisions of Decree No. 88/2014/ND-CP, enterprises providing credit rating services must be granted a Certificate of eligibility to provide credit rating services by the Ministry of Finance.

More News

Banks minimize costs, optimize profits

Banks minimize costs, optimize profits

VCN - In the first months of the year, banks' ability to optimize costs has improved significantly, especially when many banks have actively transformed digitally and cut costs in the context of a difficult economy.
Amending the law to unblock and effectively use public property

Amending the law to unblock and effectively use public property

VCN - Amending and supplementing the Law on Management and Use of Public Property will strengthen decentralization, simplify administrative procedures, increase initiative and self-responsibility for grassroots units to perform assigned tasks. Along with that, decentralization will be linked with increased inspection and supervision by competent agencies.
Pressure on exchange rate plunges

Pressure on exchange rate plunges

VCN – The State Bank of Vietnam (SBV) has taken measures including intervening in the foreign exchange market and tightening liquidity to reduce pressure on the Vietnamese dong exchange rate.
Corporate bond trading floor develops strongly after one-year operation

Corporate bond trading floor develops strongly after one-year operation

VCN - After nine-month preparation, the centralized trading system of privately placed corporate bonds has officially run at the Hanoi Stock Exchange (HNX) on July 19, 2023. After one-year operation, the system has operated safely and smoothly, the scale of privately placed corporate bond trading market has developed strongly, along with the improvement of the placement of private corporate bond in the primary market.
Closely and effectively managing State fund

Closely and effectively managing State fund

VCN - Following the socio-economic management policies and the state budget estimate for 2024, the State Treasury has managed the state fund proactively, publicly and effectively, thereby ensuring the state budget balance.
New eTax Mobile application 3.2.0 officially launched

New eTax Mobile application 3.2.0 officially launched

VCN – The General Department of Taxation has launched the latest version of the eTax Mobile application 3.2.0, which simplifies tax payment process, provides many outstanding utilities to help taxpayers use more quickly, easily and safely.
Vietnam and Japan promote cooperation

Vietnam and Japan promote cooperation

VCN - On August 28, Deputy Prime Minister and Minister of Finance Ho Duc Phoc had a working session with the Japanese Senate delegation led by Mr. Nakanishi Yusuke, Senator of the Liberal Democratic Party.
Crypto Assets should be managed rather than prohibited

Crypto Assets should be managed rather than prohibited

VCN – The issuance of legal regulations related to crypto asset management contributes to protecting investors, enhancing tax collection capabilities and improving the ability to control money laundering activities, according to experts.
Promptly disseminate policies and enhance effectiveness of state management of prices

Promptly disseminate policies and enhance effectiveness of state management of prices

VCN – Currently, the legal system on prices has been comprehensively completed, improving the effectiveness of state management of prices by ministries, branches and localities.
Read More

Your care

Latest Most read
Continue to publicly disburse public investment capital, many key projects have low rates

Continue to publicly disburse public investment capital, many key projects have low rates

The Ministry of Finance continues to publicize the disbursement rate of public investment capital plans of many key projects, notably that many projects and component projects have very low disbursement rates.
Public investment disbursement rate in 8 months reaches about 40.5% of the plan

Public investment disbursement rate in 8 months reaches about 40.5% of the plan

VCN - The disbursement for the Socio-Economic Recovery and Development Program is VND 4,931.4 billion (reaching 79.32% of the plan assigned by the Prime Minister), the National Target Program is VND 13,812.4 billion (reaching 50.74% of the plan assigned b
State revenue in 8 months increased by about 18%

State revenue in 8 months increased by about 18%

VCN - According to the Ministry of Finance, the total revenue is estimated at VND101.3 trillion, meeting 6% of the estimate, and 57.5% of the average revenue of the first 7 months of the year.
Challenges of collecting e-commerce tax losses

Challenges of collecting e-commerce tax losses

Digital transformation is an inevitable trend that changes the way goods and services are consumed and supplied, especially activities on digital platforms, making tax management more complicated.
Green finance brings both new opportunities, challenges to Vietnam: Experts

Green finance brings both new opportunities, challenges to Vietnam: Experts

The promotion of green and sustainable financial development has created both new opportunities and challenges for the financial system in Vietnam, according to experts.
Mobile Version