Public investment disbursement rate in 8 months reaches about 40.5% of the plan
Public investment disbursement in 7 months lower than same period last year | |
Transport sector plans to reach public investment disbursement rate of 98% this year |
The estimated payment for public investment in the first 8 months of the year reached 37.01% of the 2024 plan. Illustrative photo: Internet |
According to the Ministry of Finance, as of August 31, the payment is estimated at VND 274,501 billion, reaching 37.01% of the plan in 2024, reaching 40.49% of the plan assigned by the Prime Minister, lower than the levels of 39.5% and 42.35%, respectively in the same period last year.
The disbursement for the Socio-Economic Recovery and Development Program is VND 4,931.4 billion (reaching 79.32% of the plan assigned by the Prime Minister), the National Target Program is VND 13,812.4 billion (reaching 50.74% of the plan assigned by the Prime Minister).
The Ministry of Finance’s report shows that over the eight months, there were 13 ministries, central agencies and 35 localities have estimated disbursement rates higher than the average rate of the whole country.
The ministries, central agencies and localities have high disbursement rates, including: Vietnam Television (100%), Voice of Vietnam (60.72%), Ministry of Agriculture and Rural Development (58.39%), Vietnam Women's Union (52.7%), Ministry of Transport (49.67%), Long An (79.35%), Ha Tinh (64.98%), Thanh Hoa (64.05%), and Hoa Binh (60.37%).
Capital for the Socio-Economic Recovery and Development Program achieves a high disbursement rate, reaching 79.32% of the plan. Notably, the disbursed capital rate by ministries and central agencies in the 8 months reached 99.77% (the Ministry of Public Security and the Ministry of Transport alone have a disbursement rate of 100%).
However, there are still 31 ministries, central agencies and 28 localities have disbursement rate lower than the average rate of the whole country. Notably, some ministries and central agencies have a disbursement rate of 0% such as the Vietnam Cooperative Alliance and the Vietnam Fatherland Front Committee. Some ministries and central agencies have very low disbursement rates such as: the Ethnic Committee (1.12%), Hanoi National University (2.96%), Ho Chi Minh National University (4.11%), and Ministry of Science and Technology (5.52%)...
Some localities have a disbursement rate of less than 25% such as Ho Chi Minh City (16.58%), Phu Yen (18.76%), Kon Tum (21.58%), Bac Ninh (21.8%), and Quang Ngai (22.8%).
The Ministry of Finance, the low disbursement rate of some localities that have large disbursement plans, have greatly affected the overall disbursement rate of the whole country. For example, Ho Chi Minh City is assigned the disbursement worth VND79,263.78 billion, accounting for 11.8% of the plan assigned by the Prime Minister for the whole country but the city has only disbursed 16.58%; Hanoi is assigned VND81,033 billion, accounting for 12.1% of the plan assigned by the Prime Minister, but it has only disbursed 35.23%.
To achieve the target of disbursing public investment in 2024 at least 95% of the capital plan, the Ministry of Finance requests ministries, central agencies and localities to drastically implement the tasks and solutions to promote the disbursement of public investment of the Prime Minister prescribed in Directive No. 26/CT-TTg dated August 8, 2024.
The Ministry also proposes the Ministry of Planning and Investment to promptly submit to the Prime Minister adjustments to the central budget investment plan in 2024 among ministries, central agencies and localities immediately after the National Assembly Standing Committee issues an adjustment Resolution.
Related News
Accelerate implementation of solutions to disburse public investment capital
09:25 | 02/10/2024 Finance
Continue to publicly disburse public investment capital, many key projects have low rates
09:01 | 07/09/2024 Finance
More than VND241 trillion of public investment capital has been paid through the State Treasury
10:10 | 26/08/2024 Finance
Public investment disbursement in 7 months lower than same period last year
13:44 | 01/08/2024 Finance
Latest News
Stock market sees notable recovery amid ongoing uncertainties
14:14 | 14/10/2024 Finance
E-commerce tax collection in Hanoi increased by 265%
10:28 | 13/10/2024 Finance
Solving necessary and urgent issues in financial and budgetary sectors
10:57 | 12/10/2024 Finance
Banks reduce profit expectations for 2024
14:54 | 11/10/2024 Finance
More News
A new tax management approach needed to promote business household development
09:19 | 11/10/2024 Finance
Fifteen Vietnamese banks named in the global top 500 banking brands
15:23 | 10/10/2024 Finance
Digital infrastructure strategy approved
15:21 | 10/10/2024 Finance
Drastically handle tax debts in the last months of the year
09:41 | 10/10/2024 Finance
Realized social investment capital is estimated at VND2,417.2 trillion
14:22 | 09/10/2024 Finance
State-owned banks struggle to increase capital
14:19 | 09/10/2024 Finance
State budget revenue reached 85.1% of estimate
10:17 | 08/10/2024 Finance
Budget expenditure in the first three quarters of 2024 reached about VND 1,256.3 trillion
10:13 | 08/10/2024 Finance
Increasing institutional investors – improving quality of corporate bond market
10:52 | 07/10/2024 Finance
Your care
Stock market sees notable recovery amid ongoing uncertainties
14:14 | 14/10/2024 Finance
E-commerce tax collection in Hanoi increased by 265%
10:28 | 13/10/2024 Finance
Solving necessary and urgent issues in financial and budgetary sectors
10:57 | 12/10/2024 Finance
Banks reduce profit expectations for 2024
14:54 | 11/10/2024 Finance
A new tax management approach needed to promote business household development
09:19 | 11/10/2024 Finance