Applying sanctions to handle violations in finalization of completed projects

VCN - Despite instructing and urging at the same time, the settlement of completed projects is still delayed and has many shortcomings. Even the situation that many units refuse to report the settlement of these projects is still frequent. To overcome this, the Ministry of Finance will deploy many strong solutions to handle violations.

Complete many customs policies and big projects during Covid-19 pandemic
Tax sector strengthens online tax finalization support
Tax finalization in Hanoi: Urgent, serious but not negligent against Covid-19 epidemic

Applying sanctions to handle violations in finalization of completed projects
Many projects have slow disbursement progress due to incomplete acceptance, handover and settlement of completed projects. In the photo: Cat Linh - Ha Dong urban railway project. Photo: ST


Only 70% offinal settlement is required

The Ministry of Finance has summarized the report data of 125 of 143 units on the settlement of completed projects in 2019, including 43 of 54 ministries, central agencies and agencies, 19 of 26 groups, and State companies and all 63 provinces and cities directly under the Central Government.

The combined results show that the aforementioned 125 units have completed 95,303 projects with a total approved investment value of VND2,160,151 billion, of which 66,665 projects have been approved for final settlement (accounting for 70% of the total projects completed) with total approved investment value of VND981,501 billion and approved settlement value of VND773,094 billion. The number of unapproved accounts is 29,038 projects (accounting for 30% of the number of completed projects) with a total investment of VND1,178,650 billion.

Through the verification and approval of the settlement of the project, the settlement agency of ministries, branches, groups, corporations and financial agencies at various levels of the city will be removed from the proposed value, accounting for VND3,594 billion, accounting for 0.46% of the total value proposed for settlement. In fact, many projects are behind schedule for disbursement due to incomplete acceptance, handover and settlement of completed projects. In particular, there are a number of projects such as the project connecting the central region of the Mekong Delta, the project of Cat Linh - Ha Dong urban railway, the Ho Chi Minh road project, Chu Se bypass.

The State Treasury units at all levels always coordinate closely and guide the units in completing the dossiers, as well as procedures for advance and payment, ensuring that all dossiers and documents are eligible for capital payment. Investments sent by investors and project management boards to the treasuries shall be settled strictly according to the prescribed regime and time. At the same time, the Treasury also urges the investors and the project management board to speed up the project progress, take over the acceptance when the completed volume and complete the dossier of procedures sent to the Treasury to control the payment and recovery of advance capital, avoiding accumulation at the end of the year, which causes difficulties for expenditure control and disbursement.

Synchronous management mechanism

Facing this fact, the Ministry of Finance has sent a written request to the heads of ministries, central agencies, corporationsand People's Committees of provinces and centrally run cities to review and clarify theresponsibilities of organizations and individuals that do not send the financial statement of completed projects in 2019 to the Ministry of Finance as prescribed. On that basis, soon complete the report sent to the Ministry of Finance. In addition, it is necessary to direct relevant agencies to review and remedy the shortcomings of the completed project settlement reports, especially units that have existed since 2018.

Ministries, branches, localitiesand corporations should direct professional agencies, investors and relevant units to strictly implement the regulations in the settlement of completed projects; resolutely apply the handling sanctions guided in the current legal documents to violating investors and contractors. At the same time, directing the investor, the project management board and relevant units to accelerate the formulation, verification and approval of the settlement of completed projects strictly according to the regulations of the Ministry of Finance; resolutely direct quick handling and reducing the backlog of annual completed projects; direct and prioritize the arrangement of resources (personnel, material) for the verification of the settlement of completed projects.

For units in charge of verifying and settling final accounts, the Ministry of Finance shall propose to prioritize allocating reasonable resources for the verification of the settlement of completed and proactive projects in the summary of reports and guide investors and project management boards to make completed project settlement reports according to the regulations.

For investors, project management boards and contractors, it is necessary to strictly abide by the regulations on the time for making dossiers of final settlement of completed projects; improve capacity, comply with state regulations on management of investment projects; actively coordinating with the settlement examination agency to supply information in the stage of final settlement verification; manage and keep records in accordance with regulations to ensure sufficient records when project settlement is completed. In addition, the contractor should actively coordinate with the investors, prepare and provide documents as prescribed to perform the settlement of completed projects.

Recently, the Ministry of Finance issued Circular No. 10/2020 / TT-BTC stipulating the settlement of completed projects using state capital to limit and overcome problems and inadequacies in project settlement,which are completed over time.

Besides, to resolve more thoroughly, the Ministry of Finance has drafted a decree to submit to the Government regulations on management, payment and settlement of projects using public investment capital to complete the mechanism, management of payments, settlement with the scope of public investment capital in accordance with the Law on Public Investment 2019. This draft contains all specific provisions on the policy on management and payment of public investment capital, on checking allocation, advance, and payment of capital; on the settlement of the situation of the use of public investment capital from the annual state budget.

Proposing ministries and sectors urgently deploy projects that have been allocated capital, ensuring disbursement progress of investment capital

VCN - According to the latest report of the State Treasury, basically, disbursement of construction investment capital ...

Notably, the draft decree clearly stipulates the regime of reporting, inspecting and handling violations, and powers and responsibilities of organizations and individuals in finalizing completed projects.

By HongVan/Bui Diep

Related News

Warning about impersonating tax authorities to commit fraud during  tax finalization month

Warning about impersonating tax authorities to commit fraud during tax finalization month

VCN - The Tax industry has continuously provided information and issued warnings about impersonating tax officials and tax authorities to commit fraud against taxpayers, but there are still people who fall into the trap of these fraudsters, especially during the peak month of tax settlement.
Efficiency from State investment credit line

Efficiency from State investment credit line

VCN - With changes in the method of determining lending interest rates, along with regulations aimed at liberalizing conditions and authority of the Vietnam Development Bank (VDB), access to State investment credit is expected to become more convenient.
"Closing" 2023, public investment disbursement reached 93.12% of the assigned plan

"Closing" 2023, public investment disbursement reached 93.12% of the assigned plan

VCN - According to a report from the Ministry of Finance, the estimated payment for public investment capital of the whole country by the end of January 31, 2024 (the deadline for disbursement of the 2023 capital plan) reached 82.47% of the year plan and reached 93.12% of the plan assigned by the Prime Minister.
Financial policy promotes green economic development

Financial policy promotes green economic development

VCN - To realize the goal of reducing net emissions to zero by 2050 as committed at COP26, Vietnam is urgently concretizing this commitment before the international community. Regarding the Finance sector, recently, the Ministry of Finance has promoted the completion of financial policies to concretize policies and create conditions for green economic development.

Latest News

Strictly monitor market fluctuations to appropriately adjust prices

Strictly monitor market fluctuations to appropriately adjust prices

VCN – In the second quarter and the remaining months of 2024, the price management and administrations need to effectively control inflation and remove difficulties for production and businesses, the Ministry of Finance reports.
Closely monitoring market fluctuations to consider appropriate time to adjust prices

Closely monitoring market fluctuations to consider appropriate time to adjust prices

VCN - According to a report from the Ministry of Finance, in the second quarter and the remaining months of 2024, price management and administration need to ensure good control of inflation and continue to remove difficulties for production and business.
How does the Land Development Fund work effectively?

How does the Land Development Fund work effectively?

VCN - Speaking at the Conference to collect opinions on the draft Government Decree regulating the Land Development Fund held by the Ministry of Finance on April 22, Deputy Minister of Finance Bui Van Khang emphasized the necessity of the development of the Government Decree regulating the Land Development Fund.
Vietnam seeks to remove obstacles in upgrade of securities market

Vietnam seeks to remove obstacles in upgrade of securities market

The State Securities Commission of Vietnam (SSC) recently held an online working session with the World Bank (WB) and the Asia Securities Industry and Financial Markets Association (ASIFMA) to discuss ways to remove obstacles related to criteria for upgrading the Vietnamese securities market.

More News

Price stability from supply increase and transparency in trading in gold market

Price stability from supply increase and transparency in trading in gold market

VCN - To stabilize the gold market, economic expert Prof.Dr. Tran Tho Dat, a member of the Prime Minister's Economic Advisory Group, said that it is necessary to implement solutions to make all transactions transparent in the gold market, implement electronic invoices as well as pay taxes in gold investment activities.
SBV takes more actions to stabilise foreign exchange rates

SBV takes more actions to stabilise foreign exchange rates

The State Bank of Vietnam (SBV) on April 23 took some moves like issuing treasury bills (T-bills), further employing T-bills as an open market operation (OMO), and stipulating liquidity and interest rates in the inter-bank market in the face of surging USD/VND exchange rates.
Proposal to exclude criminal liability for tax officials when businesses provide false information to refund VAT

Proposal to exclude criminal liability for tax officials when businesses provide false information to refund VAT

VCN - The revised Draft Law on Value Added Tax (VAT), besides inheriting many provisions from the current Law, also revises and supplements several contents to suit the actual situation, including some notable contents in VAT refund.
Corporate bond maturity in 2024 remains high: MoF

Corporate bond maturity in 2024 remains high: MoF

The volume of corporate bonds maturing in 2024, though lower than that in 2023, is till at a high level, mostly in industries with payment risks such as real estate and renewable energy, according to a report by the Ministry of Finance (MoF).
Support clearance procedures for imported gold for bidding

Support clearance procedures for imported gold for bidding

VCN - The State Bank (SBV) has sent a document to competent ministries and branches requesting coordination in implementing the Prime Minister's direction in gold market management.
The exchange rate will gradually cool down from the end of the second quarter of 2024, while interest rates will remain low

The exchange rate will gradually cool down from the end of the second quarter of 2024, while interest rates will remain low

VCN - According to forecasts, Vietnam's financial sector in 2024 will be more positive, with the exchange rate gradually cooling down from the end of the second quarter of 2024, while interest rates will remain low to promote growth.
Majority of credit institutions forecast profit growth in 2024

Majority of credit institutions forecast profit growth in 2024

A total of 86.2% of credit institutions expect their profit this year to grow compared to 2023, according to the latest survey of the State Bank of Vietnam (SBV).
Central bank plans to auction gold bars on April 22

Central bank plans to auction gold bars on April 22

The State Bank of Vietnam (SBV) will auction SJC-branded gold bars on April 22, a representative of the central bank said on April 19.
Old loans must endure higher interest rates temporarily: central bank

Old loans must endure higher interest rates temporarily: central bank

The average lending interest rate for new loans by commercial banks is reported at around 6.4% per year, a decrease of 0.7 percentage point per year compared to the end of last year. However, borrowers with loans issued before the latest rate adjustment still must pay higher rates, according to the State Bank of Vietnam (SBV).
Read More

Your care

Latest Most read
Strictly monitor market fluctuations to appropriately adjust prices

Strictly monitor market fluctuations to appropriately adjust prices

VCN – In the second quarter and the remaining months of 2024, the price management and administrations need to effectively control inflation and remove difficulties for production and businesses, the Ministry of Finance reports.
Closely monitoring market fluctuations to consider appropriate time to adjust prices

Closely monitoring market fluctuations to consider appropriate time to adjust prices

VCN - According to a report from the Ministry of Finance, in the second quarter and the remaining months of 2024, price management and administration need to ensure good control of inflation and continue to remove difficulties for production and business.
How does the Land Development Fund work effectively?

How does the Land Development Fund work effectively?

Deputy Minister of Finance Bui Van Khang emphasized the necessity of the development of the Government Decree regulating the Land Development Fund.
Vietnam seeks to remove obstacles in upgrade of securities market

Vietnam seeks to remove obstacles in upgrade of securities market

The State Securities Commission of Vietnam (SSC) recently held an online working session with the World Bank (WB) and the Asia Securities Industry and Financial Markets Association (ASIFMA) to discuss ways to remove obstacles related to criteria for upgrading the Vietnamese securities market.
Price stability from supply increase and transparency in trading in gold market

Price stability from supply increase and transparency in trading in gold market

VCN - To stabilize the gold market, economic expert Prof.Dr. Tran Tho Dat, a member of the Prime Minister's Economic Advisory Group, said that it is necessary to implement solutions to make all transactions transparent in the gold market, implement electr
Mobile Version